Sample Practice Exam Questions
Three programming activities must be completed on time in order to begin
testing on time. The first two activities have a 0.90 probability of being
completed by the due date. The third has a 0.80 probability of being
completed on time. What is the probability of starting the testing on time?
Answer A Probability = product of all the individual probabilities = 0.9 X 0.9 X 0.8.
(PMBOK Guide 11.4.2
Quantitative Risk Analysis: Tools and Techniques) Process = Planning, Process Group = 11.4
Quantitative Risk Analysis, Knowledge Area = Risk
Answer A
is a specific example of legitimate high quality PM performance.
Answer B is not always true because it is legitimate to acquire a good reputation (personal gain)
through consistent high quality PM performance. Answer D is not true because it is your job as
project manager to select those individuals who can best do the job at hand -- your only personal
gain is better performance of the project for which you are responsible. The pattern is a variation
of what the PM should do and asks you to distinguish between closely related answers. This question
tests your ability to demonstrate your understanding of the relationship among facts, principles and
processes. Professional Responsibility. See the
Code of Ethics and Professional Conduct.